Early contractor involvement
On traditional construction contracts, the client first appoints consultants to design the project in detail, and then a contractor is appointed to construct the works.
However, this can be seen to be a somewhat fragmented and adversarial project structure which does not give the contractor the opportunity to contribute to the development of the design that they will be required to construct.
Civil Engineering Procedure 7th Edition, published by the Institution of Civil Engineers (ICE) suggests that early contractor involvement (ECI) denotes ‘…a non-traditional procurement route, where a contractor’s skills are introduced early into a project to bring design ‘buildability’ and cost efficiencies to the pre-construction phase’.
Typically, early contractor involvement might be enabled by a two-stage tender process, used in the first stage to procure contractor involvement in the design process, and in the second stage to procure construction of the works. Other procurement routes, such as design and build, construction management, or management contracting might also allow a contractor to become involved in the design stage.
Early contractor involvement can enable the contractor to:
- Contribute to the design process.
- Build a better team-working ethic.
- Introduce innovations.
- Advise on buildability, sequencing, and construction risk.
- Advise on the packaging of the works.
- Advise on the selection of specialist contractors.
- Spend more time developing a construction strategy, recruiting staff, identifying partners and so on.
- Help develop the cost plan and construction programme.
- Help develop the method of construction.
- Obtain prices for work packages from sub-contractors or suppliers on a open-book basis.
- Prepare a site layout plan for the construction stage.
- Draft the preliminaries for specialist and trade contractor bid documents.
- Assist with planning applications on matters concerning the build phase, such as waste disposal, construction traffic movements and tree protection.
ECI is particularly well-suited to large or complex projects, but can be adopted on any project.
The use of a Pre-Construction Services Agreement (PCSA, sometimes referred to as Pre-Contract Services Agreements) can enable the client to employ a contractor before the main construction contract has commenced.
The NEC3 Engineering and Construction Contract (ECC) Options C and E also include provisions for early contractor involvement. See NEC early contractor involvement for more information.
Early contractor involvement may require that the contractor undertakes the early design stages themselves, or that they simply contribute to the design development which is undertaken by others. There can sometimes be a degree of ambiguity about precisely what the contractor is expected to do in these stages, and this can cause confusion and dissatisfaction.
Another perceived disadvantage of early contractor involvement is that the contractor becomes involved in the project before it has been designed in detail, and so they are unable to give an accurate price for the construction works. While contracts generally provide for some element of transparency and competition in the second state appointment, the reality is that other tenderers may have lost interest in the project, and the embedded contractor will have a significant competitive advantage.
The earlier the contractor is appointed, the greater the potential benefits they are able to bring to the project, but the less able they are to provide accurate pricing information for the second-stage tender process. Also, the second stage is likely to be.less competitive.
[edit] Related articles on Designing Buildings Wiki
- Adversarial behaviour in the UK construction industry.
- Appointing consultants.
- Civil Engineering Procedure.
- Construction contract.
- Construction management.
- Contracting.
- Design and build.
- Design and manage procurement route.
- Early appointment / involvement.
- Integrated project team.
- Management contract.
- NEC early contractor involvement.
- Open book accounting.
- Optimised contractor involvement.
- Pre-construction services agreement.
- Procurement route.
- Single-stage tender.
- Tender.
- Tender processes.
- Two stage open book.
- Two stage tender.
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 2 June
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.
The adaptive reuse of large industrial structures.
Promoting the circular economy by extending the life of buildings.
CIAT responds to Climate Change Committee report
An urgent wake-up call for both government and the built environment.
Construction Management, 24 June
FMB pilot aims to build pipeline of site-ready tradespeople.
A quick introduction.
CLC publishes Mental Health Joint Code of Practice.
A quick introduction to its uses and risks.

















